Now that the shipping container has gone from our driveway we had a dumpster bin delivered, and hired a dingo for the day. I managed to
excavate and level the front yard, and
clean up down the side. I got it all fairly level and straight, but I excavated just a little bit too much in one spot and bent the gas pipe, and knocked over the front tap. We’ll have to get the plumber out to fix them. Oh well.
Next weekend’s job is the retaining wall. I’ll have 30m of 150x75 treated pine sleepers, and 2T of extra earth delivered for this.
Well, I haven’t updated in a while, (around 1 month). But then again not much has changed. This is always the way. Once you move in everything grinds to a halt. Besides; I needed to spend some time with my family. Floors: We’ve received the second load of flooring. This flooring hasn’t been milled as acurately as the old stuff so I’ve had to buy a proper flooring gun. This pushes the board in at the same time firing a nail in. The gun is the same as a normal nail gun, but the firing mechanism is a bolt at the top that gets hit with a hammer. This then fires a nail at 40 degrees into the tongue. Bathroom: We’ve been using two partially complete bathrooms. I have yet to complete the tiling around the bath area, and get the plumber back to connect the shower up properly, (I’m using a spanner as a tap at the moment). Architraves: They’re not up, but I have to finish the flooring first. These will go in easily with my old paslode. I’m putting in removeable mitre-less skirting boards. These will allow me to remove them for termite inspections. Dingo: I’ll be getting the dingo back tolandscape the ground. I need to get rid of the rubble out the front and shift a whole swag of dirt around.
Verandah: I’ll need to finish off the above first. Then I’ll get the concretor back to lay the concrete for the front verandah. Then I can put up the verandah.
After all this it’ll be finished. Hooray!
Back on to the trenching. We
chucked in the pipes,
had the odd smoko,
thought about how little money we have now, and
put in the ag pipe.
Later we filled in the trench and half covered the pipes ready for inspection.
The plumber came today to do a couple of things. I was also there helping him out with the storm water trenches and retaining pit. We had 9 tonnes of 25mm blue metal dumped and we shifted most of it into the
trenches and pits. If I had tried to do that last year I would have had a really sore back and muscles, (being an IT geek I tend to just sit in a chair all day), but since I’ve been building I’m used to it now. I’m down to 75kg now, so it just goes to show what a bit of rigourous continuous exercise does for you.
It’s time for the servics to go in. I had spent some time deciding whether to go DSL or stick with Optus. The ongoing costs are cheaper with DSL, so I transferred my phone over to Telstra, (a pre-req for getting DSL), bought a modem, and rang up the subbie to get my DSL line installed. BUT! I have no idea where the Telstra line is anymore, and the subbis is going to charge $120 callout and $20/15min. Aaaargh! I cancelled the switch and stuck with Optus.
I rang Optus up, they came out and gave me a quote for $280 for the underground cable. They gave me a sheet on what I had to do which is basically do everything up to the point of installing the cable. So I spent Sunday digging out the power trench and laying 32mm Telco conduit. I bought extra conduit and put that in the trench as well. You never know WHEN you might need it.